Total Authorized:
$534,750,000
Total Issued:
$432,050,000
Total Unissued:
$102,700,000
Note: Authorizations and issuances for refunding are excluded from totals.

05/04/2024

Prop Purpose Amount For/Against Issued Unissued
A School Building Improvements $102,700,000 2,350 (55.7%) / 1,868 (44.3%) $0 $102,700,000
B Athletic Improvements $68,800,000 1,995 (47.5%) / 2,208 (52.5%) N/A N/A
C Aquatic $19,600,000 1,931 (46.0%) / 2,264 (54.0%) N/A N/A
D School Building $27,000,000 1,969 (47.1%) / 2,215 (52.9%) N/A N/A
Total $218,100,000 $0 $102,700,000

05/07/2022

Prop Purpose Amount For/Against Issued Unissued
A School Building/Athletic Improvements $143,045,000 2,173 (56.3%) / 1,689 (43.7%) $143,045,000
Issued Dated Date
$143,045,000 07/15/2022
$0
B Stadium $62,570,000 1,892 (49.0%) / 1,969 (51.0%) N/A N/A
C Aquatic $19,390,000 1,922 (49.8%) / 1,934 (50.2%) N/A N/A
Total $225,005,000 $143,045,000 $0

11/03/2020

Prop Purpose Amount For/Against Issued Unissued
A School Building $100,150,000 8,767 (54.1%) / 7,426 (45.9%) $100,150,000
Issued Dated Date
$100,150,000 03/15/2021
$0
Total $100,150,000 $100,150,000 $0

11/03/2015

Prop Purpose Amount For/Against Issued Unissued
1 School Building $109,500,000 2,313 (60.9%) / 1,488 (39.1%) $109,500,000
Issued Dated Date
$70,000,000 03/01/2016
$39,500,000 04/15/2017
$0
Total $109,500,000 $109,500,000 $0

11/07/2006

Prop Purpose Amount For/Against Issued Unissued
1 School Building $31,710,000 3,229 (53.8%) / 2,771 (46.2%) $31,710,000
Issued Dated Date
$19,110,000 04/15/2007
$7,200,000 02/01/2008
$5,400,000 09/01/2008
$0
2 Safety $8,275,000 3,199 (53.8%) / 2,748 (46.2%) $8,275,000
Issued Dated Date
$250,000 04/15/2007
$6,650,000 02/01/2008
$1,375,000 09/01/2008
$0
Total $39,985,000 $39,985,000 $0

02/10/2001

Prop Purpose Amount For/Against Issued Unissued
1 School Building $25,210,000 715 (57.0%) / 539 (43.0%) $25,210,000
Issued Dated Date
$15,000,000 06/15/2001
$10,210,000 11/01/2002
$0
Total $25,210,000 $25,210,000 $0

12/06/1997

Prop Purpose Amount For/Against Issued Unissued
1 School Building Improvements $14,160,000 551 (55.0%) / 451 (45.0%) $14,160,000
Issued Dated Date
$14,160,000 02/01/1998
$0
Total $14,160,000 $14,160,000 $0

03/14/1992

** Not included in totals because remaining authorizations are considered to be too old or too small
Prop Purpose Amount For/Against Issued Unissued
1 School Building $20,500,000 (Vote counts are unknown) $20,498,702
Issued Dated Date
$20,498,702 05/15/1992
$1,298
Total $20,500,000 $20,498,702 $1,298