Prop | Purpose | Amount | For/Against | Issued | Unissued |
---|---|---|---|---|---|
A | School Building | $34,500,000 | 467 (78.1%) / 131 (21.9%) | $0 | $34,500,000 |
Total | $34,500,000 | $0 | $34,500,000 |
Prop | Purpose | Amount | For/Against | Issued | Unissued |
---|---|---|---|---|---|
A | School Building | $9,870,000 | 236 (46.5%) / 272 (53.5%) | N/A | N/A |
B | Renovations | $2,390,000 | 246 (48.6%) / 260 (51.4%) | N/A | N/A |
C | School Building Improvements | $680,000 | 227 (44.8%) / 280 (55.2%) | N/A | N/A |
Total | $12,940,000 | N/A | N/A |
Prop | Purpose | Amount | For/Against | Issued | Unissued |
---|---|---|---|---|---|
1 | School Building | $12,500,000 | 168 (42.3%) / 229 (57.7%) | N/A | N/A |
Total | $12,500,000 | N/A | N/A |